Renewable energy developers get one-time exit for unused grid connectivity

This move aims to free up grid capacity for projects ready for commissioning. The regulator estimates 15.7 GW of connectivity could be released through this initiative. Developers retaining connectivity without a PPA must furnish a bank guarantee and commission projects within 24 months.

Jul 15, 2026 - 01:30